|
Introduction
This paper proposes a framework for the evaluation of Information System (IS)
innovation projects. By innovation projects we mean those projects that involve
adopting technology which allows an organization to do things in new ways and
where the organization's prior experience of the IS products or services is low.
These projects exhibit a tight, iterative coupling between IS design and use and
closely follow an innovation process. Our observation of these types of project
revealed that the methods used in their evaluation differed in several respects
from those described in the current literature. Evaluation processes described
in the literature are broadly external to the project; yet, we observed
processes which were both tightly integrated within the project and highly
dynamic - a kind of "bootstrapping" process of learning. Evaluation in
the literature implies that once a system is developed and implemented it is
"good" if it requires little subsequent change; our observations
suggested that in innovation projects it is often not until practical experience
in using the system has been gained that the requirements are really understood.
The evaluation literature says little about changes in the underlying technology
products, implicitly assuming them to be stable; we observed that not only were
products changing but that organizations sought opportunities to influence the
direction of change to be favourable to themselves.
In the following sections, a framework for the evaluation of IS innovation
projects is developed and applied to a case study of electronic data capture for
clinical trials at Glaxo Wellcome Research & Development.
Key features of an "IS innovation project"
There are three key features of an IS innovation project:
· The project follows an innovation process, with its three phases of
initiation, adoption and implementation (Rogers, 1983). (The key point here is
the need for evaluation techniques to place emphasis on the implementation phase
- traditional techniques tend to view implementation as the final step in the
process which is hardly elaborated upon).
· There is tight coupling between the design and use of the IS product or
service (Orlikowski 1992).
· The organization's prior experience of the product or service is low.
We do not restrict innovation to early adopters: if the technology applied is
new to the organization, it is considered to be an innovation even if it is well
established elsewhere (Rogers 1983; Swanson 1994). However, we do restrict the
scope to the consideration of new IS products or services: new IS work
technologies or administrative arrangements are not included.
The purpose and timing of evaluation in IS innovation projects
Evaluation in innovation projects may be carried out for the same purposes as in
conventional projects, i.e. for justification, as part of project control or for
the purposes of learning for future projects or for future evaluation (see for
example Farbey et al. 1993). However, in IS innovation projects, the purposes
are extended to include evaluation of the development of organization-technology
fit - this type of evaluation can be thought of as a mechanism for coupling
between design and use and a tool for continuous learning and improvement.
Whilst project justification remains important, a more incremental approach is
taken with a number of separate decisions, such as those associated with funding
feasibility studies, setting up of pilots, initial implementation and subsequent
roll-out. Decisions are also likely to be subject to review as circumstances
change.
Project monitoring and control and post-project review will both be similar to
that for conventional IS projects but the underlying project process will, of
course, be different.
The evaluation life-cycle for traditional and innovation projects is similar in
the very early stages and during routine operational use. However, significant
differences occur during the development and implementation phases which are
separate in the traditional life-cycle but tightly integrated in an IS
innovation project.
Figure 1 summarises the purpose and timing of evaluation in IS innovation
projects. Each type of evaluation is discussed in more detail in the next
sections of the paper.
Developing organization-technology fit
Initial evaluation
Initial evaluation occurs at the agenda-setting stage of the IS innovation
process and may be driven either from the perceived need for a solution to a
specific business problem or from the awareness of a potentially valuable new IS
product or service.
In the problem-focused case, the first target of evaluation is likely to be the
development of a clearer understanding of the problem. Thereupon, an active
search for solutions can be undertaken and the focus of evaluation will then
move to the development of "awareness knowledge". This consists of
"principles knowledge" and "how-to knowledge" for each
potential solution (Rogers, 1983).
In the technically-focused case, awareness of a new IS product or service may
occur:
· through routine monitoring of technological advances
· as a result of publicity or contact from potential providers of a particular
product or service
· through monitoring of competitors or as a result of routine professional
contact
Figure
1: The purpose and timing of evaluation in IS innovation projects

The focus will then move to identifying
and developing an understanding of relevant business problems that the product
or service may address.
In both of these cases, the information
gathered may be used to justify funding for the next stage of the project,
possibly allowing for trialing of the most promising solutions. Evaluation is
likely to be iterative, with the emphasis shifting between internal and external
foci as knowledge of both the business problem and potential solutions
increases.
Assessment, comparison and selection of options
At the matching
stage, the fit between organization and technology starts to be evaluated.
Again, the focus is on information gathering. In the problem-focused case, a
number of possible solutions may be matched against the business problem. In the
technically-focused case, potential solutions may be matched against a number of
problems to determine which, if any, should be further investigated.
Evaluation will assess the feasibility
of each solution, its flexibilities and constraints, risks and opportunities and
any obstacles to implementation. Stakeholder groups and potential costs and
benefits will need to be identified and understood. The purpose of evaluation
will be to eliminate infeasible options and to compare alternative viable
options to select the best to take forward to the adoption phase. Piloting can
be particularly valuable.
Although at a high level the IS product
or service to be implemented will have been selected by the end of the
initiation phase, it is likely that for some sub-components of the project
alternative options remain. Thus, this type of evaluation is likely to continue,
but at a more detailed level, into implementation. There may also be subsequent
re-evaluation of options in the light of experience in use.
Continuous learning and improvement
As the project moves into the redefining/restructuring
stage of implementation, the fit between the organization and the technology
continues to be evaluated and developed. Information is actively sought as more
“principles” and “how-to” knowledge is acquired through experience in
use. Not only may the product or service be adapted to better fit the
organization, but the structure of the organization and its ways of working may
have to be changed to accommodate the new product or service: evaluation can be
thought of as a feedback mechanism between use and design. If significant gaps in fit are found (these could arise
through changes either internal or external to the project or be a result of
unanticipated problems experienced in the field), it may be necessary to
re-evaluate the options.
At the clarifying
stage, as the product or service is put into wider use, the fit between
organization and technology should be well defined, although there may be minor
improvements to be made. The focus moves to supporting larger scale use. Any
misunderstandings, unwanted side effects or barriers need to be quickly
identified and assessed so that corrective action can be taken.
At the routinising
stage, the product or service is in wide use within the organization. By this
stage, evaluation for the purpose
of developing organization-technology fit will have effectively ceased.
Project justification and decision-making
Much of the information gathered in the
development of organization-technology fit will be a source of input to project
justification and decision-making. This is an on-going process recognising that
the information upon which decisions are made will change over time.
In the agenda-setting
and matching stages, prior to any
decision to adopt a particular solution, decisions to experiment with or trial
particular options will be made on limited information. Justification for a
particular course of action may be primarily based on information buying or risk
reduction at relatively low cost. As the project progresses, however, and more
information becomes available this will be used to develop the business case.
By the end of the initiation phase, all
necessary information should have been gathered to support the decision on adoption
of an IS product or service, to plan for its initial implementation and to
justify the necessary funding. The primary purpose of evaluation at this point
is to provide the necessary support to management to enable them to take the
adoption decision. This is not necessarily a straightforward choice between
adoption and rejection of the IS product or service for several reasons:
·
Although one course of action may be preferred
and recommended, alternatives may need to be considered
·
It may be felt that the time is not right to
move forward into implementation. This may be because more information is needed
or because the plans for implementation are not yet sufficiently developed i.e.
the project effectively moves back to initiation. Alternatively, if the products
being considered are undergoing rapid changes, a “wait and see” strategy may
be better.
·
There may be choices in scale of implementation
- too large and the project can become difficult to manage and control; too
small and the full benefits will not be realised.
The timing of the adoption decision is
critical to success. If it is taken too early, with insufficient knowledge,
there is a risk that the product or service will be misused and will
consequently fail leading to disenchantment and loss of confidence. If the
decision is taken too late, the costs will be higher and the achievement of
potential benefits delayed.
An important difference between IS
innovation projects and conventional IS projects is that adoption decisions are
likely to be subject to subsequent confirmation.
This may be a pre-planned review, a response to changing circumstances
external to the project or as a result of problems during implementation. As a
consequence, evaluation will continue for the purpose of justification of the
project. As the project moves through the implementation phase, performance
targets may be set and a performance measurement programme introduced. As
experience grows and evidence is gathered, earlier assessments of costs and
benefits will be refined to strengthen the business case.
Project monitoring and control and post-project review
Evaluation for the purpose of monitoring
and control of the project will start in the matching stage, as experimentation with or trialing of potential
solutions is undertaken and associated costs start to be incurred. An important
aspect of evaluation at this stage is to ensure that the specific objectives of
experimentation are met and that the necessary principles knowledge is gathered.
At the redefining/restructuring
stage, monitoring and managing the implementation process is particularly
critical: making sure that information is communicated to the right people, that
processes and working practices are correctly followed, technical aspects run
smoothly, etc. Performance targets and measurement programmes may be instigated.
At the clarifying
stage, the focus moves to monitoring performance targets and supporting the
management of larger scale use. Any unwanted side effects or barriers to meeting
targets need to be quickly identified and assessed.
At the routinising
stage, the product or service is in wide use within the organization and the
project will be drawing to a close. Once the project has been completed, a
post-implementation review is likely to be conducted. As with conventional IS
projects, this will be primarily concerned with product and process review (Earl
1989)
.
An illustrative example: Electronic Data Capture for
Pharmaceutical Clinical Trials
To illustrate the evaluation life-cycle
for IS innovation projects we present a case study carried out in Glaxo Wellcome
Research and Development (GWRD) and, prior to the merger in 1995 of the Glaxo
Group with Wellcome plc, in Glaxo Research and Development.
The case study describes the Electronic
Data Capture (EDC) project, a major project to implement electronic data capture
tools in clinical trials. Clinical trials data have traditionally been and still
are largely collected on paper, using case record forms (CRFs), which are
completed by the investigator, or diary cards, which are usually completed by
the patient. Speeding up the clinical trials process is a key goal for Glaxo
Wellcome, in common with most other pharmaceutical companies and EDC is seen as
an important factor in achieving this goal.
An overview of the EDC project
The start of the EDC project can be
traced back to 1993 in Glaxo Research and Development, prior to the merger with
Wellcome, when a small team was set up in the UK Medical Operations Division to
review options for electronic data capture.
One of the first actions of the team was
to commission an in-house review of emerging technologies. The purpose of this
was two-fold: firstly, to identify available options and, secondly, to gain an
insight into the way other companies were implementing these technologies.
Subsequently, the team focused on fax technology and combined CRF/entry screen
design as areas offering most potential for significant business benefit. One
electronic CRF product, based on a pen-computer, was demonstrated
but it was felt that the technologies used, in particular handwriting
recognition, were not sufficiently mature at that time. The team reported their
findings in early 1994 and recommended that implementation proceed only for
fax-based CRF return but that a small pilot of an eCRF system also be
considered. A pilot implementation of the pen-computer based system was
subsequently approved.
The clinical trial chosen for the eCRF
pilot was conducted during the second half of 1994 in two European countries at
13 investigator sites. The pen-based system was found to be unsuitable for use
in its current form but the feasibility and potential benefits of eCRF systems
in principle were clearly demonstrated.
At this time, a process improvement
project was also underway in Medical Operations. Electronic data capture was
identified as an important target and was given a high priority. The decision to
go ahead with the next phase of the data capture project was taken at a senior
level before the pilot had been completed. In October 1994, the emphasis was on
putting in place a ‘dynamic framework’ of data capture tools, based on
off-the-shelf components. Bespoke systems development, either in-house or
contracted out, had been ruled out early on, so commercially available products
were evaluated and the most promising were implemented and evaluated
individually in live clinical trials.
By August 1995, when interviews for this
case study commenced, the focus of attention had moved to eCRF systems, which
were seen as offering the ability to shorten clinical development programmes by
several months. Products from three different vendors were being used in four
clinical trials, ranging from a short, single-site clinical pharmacology study
in the US to a major, 18-month-long Phase III clinical trial conducted in 50
centres in six European countries. The major objective at this stage was to
determine how to select and scale up on one eCRF system for ‘production use’
(the term used by the EDC project team for routine use within the organization).
In October 1995, a meeting was held to
review the key lessons learnt from the project’s eCRF experience to date, to
select a preferred software vendor and to plan the move into large-scale
production use of eCRFs. It was also decided to contract out the hardware
services associated with configuring, installing and supporting portable PCs in
the field. Following the review meeting, a proposal for funding for the first
two years of the production phase of the project was prepared and finally
approved in May 1996.
A contract for the provision of software
and software services was finalised with the preferred eCRF software vendor in
May 1996. The hardware service provider was selected in August 1996 and the
contract was signed in November 1996.
In August 1996, the first of a series of
joint US/UK project meetings was held to prepare for large-scale implementation
of the selected eCRF system. At the centre of this was the development and
documentation of international processes and working practices for the use of
eCRFs. Subsequent meetings in November 1996 and March 1997 extended the
objectives to include the development of training and support programmes and a
programme for routine evaluation of EDC.
Also in the second half of 1996, the
first clinical trials were selected to use the contracted-out software and
hardware services and the new processes and working practices. Initially it was
anticipated that the selected eCRF system would be implemented in 100% of Phase
I and 50% of Phase II, III and IV trials by the end of 1997. This was reassessed
as both the internal and software vendor capabilities for scaling up became
apparent and the target for the first year was revised to 50 clinical trials in
1000 sites. Experience was captured on an ongoing basis both through informal
communication between members of the EDC team and the project teams and through
the routine collection of metrics and user feedback.
At the end of 1996 the next phase of the
Medical Operations process improvement project was initiated and EDC became a
component project within Core Process Redesign (CPR). This transfer of
responsibility prompted a review of EDC within the broader context of the
redesign framework: the project justification was reconsidered and the validity
of strategy for implementing the eCRF system was re-examined and confirmed.
Over 1997, the view of the selected eCRF
solution changed as experience grew and its limitations were recognised. The
strategic focus within the organization moved to “next generation” EDC and
the investigation of future EDC solutions became a separate project.
The primary focus of the EDC project
became the implementation of the selected eCRF solution as tactical tool for use
in the short term and as a way of building skills and knowledge in preparation
for the piloting and subsequent scaling up of future EDC technologies.
Implementation proceeded steadily over the year and by December 1997 the eCRF
solution was implemented in between 10% and 15% of clinical studies.
In parallel with the implementation
activities, an EDC Transition Team was set up in May 1997 to make
recommendations on how the management and use of the selected eCRF solution
should move from the EDC project team to integration within Glaxo Wellcome line
functions. The team reported in January 1998 and its recommendations were
approved.
Overall, fourteen major evaluation
exercises were identified in the EDC project and these have been mapped against
the primary evaluation purpose in Figure 2.
Evaluating organization-technology fit
Of the major evaluation exercises
identified, nine were primarily concerned with the evaluation of
organization-technology fit. Although in most cases the information gathered was
also used to support evaluation for other purposes, this still gives a clear
indication of the importance of this kind of evaluation.
**Figure
2: Mapping of EDC evaluation exercises against evaluation purpose
Evaluation exercises:
|
1.
Review of emerging technologies
2.
Evaluation of pilot use of pen-based eCRF system
3.
Piloting of alternative eCRF products
4.
“Production review”
5.
Preparation of business case for eCRF implementation
6.
Selection of hardware service provider
7.
Routine collection of standard metrics and user feedback from eCRF
studies
|
8.
Identification and assessment of electronic systems for the capture
of diary card, quality of life and other questionnaire data
9.
Metrics reviews
10.
Re-evaluation of eCRF systems
11.
Re-evaluation of eCRF business case
12.
Assessment of criteria for determining data handling strategy
13.
Review of helpdesk and hardware service provision
14.
Metrics in routine use
|
Initial evaluation
The initial review of emerging
technologies was driven primarily from the identification of the capture and
entry of clinical data as the remaining target for potentially useful
exploitation of IT, given that data processing and reporting for clinical trials
had already been addressed. There was also an awareness that the majority of
other major pharmaceutical companies were already active in this area and that a
number of commercial products capable of conferring significant business benefit
were becoming available. The purpose of the exercise was “to review options
and to produce a proposal for the integrated use of appropriate technologies”
within a time frame of 5 months, to fit in with the organization’s internal
budget cycle. This involved identifying and developing “awareness knowledge”
of potential solutions, either commercially-available products, in-house
development or collaborative ventures with other pharmaceutical companies.
An important component of the review was
understanding how other companies were using these technologies and learning
from their experiences.
Assessment, comparison and selection of options
There were four major evaluation
exercises which were initially conducted for the purpose of assessing, comparing
and selecting options within the project: the evaluation of pilot use of the
pen-based eCRF system, the piloting of alternative eCRF products, the
“production review” and the selection of the hardware service provider.
The objectives of the pen-based eCRF
pilot were again focused on information gathering:
·
to identify by how much the technology could
shorten time to market;
·
to assess the effects of the technology on
working practices;
·
to determine the acceptability of the
technology in the clinic; and
·
to consider options for pen-based CRF
processing and their associated costs and benefits.
In the second evaluation exercise, three
different eCRF systems were piloted in four clinical trials. The focus of these
pilots was on identifying potential issues around scaling up.
The primary objective of the production
review, which drew heavily on the information gathered in the previous pilots,
was to select one or more preferred eCRF software vendor for “production
use” of EDC. Other objectives included the development of scenarios for
working processes and use of technology, determining implementation plans,
considering the further evaluation of new technology (especially for non-CRF
data) and reviewing the key lessons from the pilots. The production review was
held jointly with US and UK representatives and a great deal of time was spent
ensuring that there was a common view of the technology within the team through
sharing information and agreeing selection criteria.
Following the production review and the
identification of a preferred eCRF software vendor, the process of selecting a
hardware service provider got under way. Initially, the service requirements
were defined at a fairly high level, but these were specified in greater detail
as the selection process progressed and understanding increased through
discussion both within the EDC team and with the potential service providers.
Finally, there was one additional
evaluation exercise, the identification and assessment of electronic systems for
the capture of diary card, quality of life and other questionnaire data, which
was conducted in a sub-component of the project determining EDC options for non-CRF
data. This was carried out at a later date when the implementation of eCRFs was
well under way, with the objectives of defining requirements for different types
of diary cards and questionnaires and of identifying the most promising
potential solutions.
Continuous learning and improvement
As the EDC project moved into production
use, a programme for the routine collection of standard metrics and user
feedback from eCRF studies was set up and data was collected on an ongoing basis
for more than a year. Two metrics reviews were conducted which drew on and
summarised the evaluation data. These exercises were all strongly focused on
learning for improvement. Objectives for the routine collection of metrics and
user feedback included measuring the impact of eCRFs on clinical trial timelines
and resources, collecting feedback from various stakeholders and making
recommendations for improvement. The objectives of the first metrics review were
to take a critical look at the current status of eCRF implementation, to
demonstrate the successes and to identify the issues being addressed with the
overall aim of providing a baseline against which improvement in the use of
eCRFs could be measured over time. The second review had similar objectives,
concentrating on changes since the first review.
Later, as the EDC Transition Team was
planning for the transfer of the eCRF system into routine use, helpdesk and
hardware and software service provision was reviewed with the objectives of
revising the services to match current needs, which had changed significantly
since they were first implemented.
Project justification and decision-making
An incremental approach was taken to
justification of the EDC project. Much
of the supporting information came from the exercises concerned with the
development of organization-technology fit.
In the early stages of the project,
justification of the early fax and pen-computer pilots and the subsequent pilots
of alternative eCRF products was primarily an ‘act of faith’, recognising
that the necessary information was not yet available to build a solid business
case. In applying for funding for the pilots, the emphasis was primarily on
estimating costs, not benefits. Although some potential benefits were
identified, it was not possible to quantify them and an important objective of
the pilots was to acquire the information and understanding necessary to develop
the business case.
The adoption of the preferred eCRF
product for ‘production use’ was based on a capital expenditure proposal
which was reviewed and approved through the standard internal GWRD mechanisms in
May 1996. The proposal was supported by a cost-benefit analysis based on reduced
clinical development time and hence earlier regulatory submission and ultimately
product launch.
The transfer of responsibility for EDC
to CPR prompted a review of the project in early 1997. The project justification
was reconsidered and the validity of implementing the eCRF system was
re-examined and confirmed. The routine evaluation of the early eCRF trials
played an important part in the review by providing evidence showing that
expectations were being met and an active programme for continuous improvement
was in place. CPR placed particular emphasis on the need for a stronger
cost-benefit case as the business climate within GWRD changed.
In the second half of 1997, the EDC
Transition Team re-evaluated the eCRF business case and extended the metrics
collection to develop a clearer understanding of the costs and benefits incurred
in using the eCRF system compared to paper-based studies and CRO costs. The Team
also developed tools that could be used to support decision-making on the use of
eCRFs for future studies, drawing on the re-evaluation and on earlier work on
eCRF study selection criteria.
Evaluation for justification and
decision-making occurred throughout the life-cycle of the project; as more
information became available, understanding of the implications of EDC increased
and the business case developed to reflect this.
Project monitoring and control and post-project review
Much of the evaluation conducted
primarily for the development of organization-technology fit also provided
information which was used to support project monitoring and control. This was
particularly true of the routine collection of standard metrics, which included
data on resources, timelines and costs incurred as well as on the realisation of
benefits which could be compared with previous estimates and used to monitor
project progress.
By February 1998, when the last case
study data were collected, the project team was being disbanded and the
recruitment of staff for the new organizational structures was under way.
Evaluation was planned to continue with the objectives of routine performance
monitoring and providing information and support for decision-making on data
handling strategies. At this time, no formal post-project review was planned.
Conclusion
In our view, the evaluation of IS
innovation projects requires a different set of methods to those used for
conventional projects. This requirement stems from the fact that the underlying
project processes are different.
A critical point about an IS innovation
project is that often a full understanding of requirements can only be developed
through practical experience gained as the project evolves - the project process
is complex and iterative and evaluation is an integral part thereof. Further,
the underlying technology may be changing and this, together with any
opportunities for influencing the direction of change, needs to be understood
and accommodated.
The development of
organization-technology fit lies at the core of IS innovation projects.
Evaluation for this purpose can be thought of as a coupling mechanism between
use and design and as a tool for continuous learning and improvement. It also
provides information to support evaluation for the traditional purposes of
project justification and project control. The importance of evaluating the fit
between organization and technology on an ongoing basis from project initiation
through to routine operation is clearly illustrated in the case of Glaxo
Wellcome’s EDC project. Of the fourteen major evaluation exercises identified
in the project, nine were primarily conducted for this purpose.
This leads us to the conclusion that in
developing methods for evaluation of IS projects we need to draw more
extensively on the established body of academic literature in the field of
innovation, and extend the existing methods of evaluation to reflect more
specifically the requirements of IS innovation projects.
Acknowledgement
The authors would like to thank Glaxo
Wellcome R&D for their support in sponsoring this research.
References
-
Earl MJ (1989) Management
Strategies for Information Technology. Prentice Hall, London.
- Farbey B, Land F and Targett D (1993) How
to Assess your IT Investment. A Study of Methods and Practice. Butterworth
Heinemann, Oxford.
- Orlikowski W (1992) The duality of
technology: rethinking the concept of technology in organizations. Organization
Science 3(3),
398 - 427.
- Rogers EM (1983) Diffusion of innovations. 3rd edition. The Free Press, New York.
-
Swanson EB (1994)
Information Systems Innovation Among Organizations. Management Science 40(9),
1069 - 1092.
|